Kerbstones in the bill of quantities
| Unit | lin. m |
|---|---|
| Category | Paving |
| Division | External works and roads |
The item as worded in the bill
Supply and lay precast concrete kerbstones size 15×30×50 cm, compressive strength as specified, with smooth honeycomb-free faces, on a plain concrete bed with concrete haunching behind; the rate includes the necessary excavation, setting to line and level, pointing the joints in cement mortar and curing.
Method of measurement
Measured in linear metres along the exposed front face, curves included, without deducting joints. Small-radius curved kerbs, dropped kerbs at entrances and transition units are carried in separate items where the bill provides. Concrete bed, haunching and excavation are within the rate per linear metre and are not measured in cubic metres unless an explicit item exists.
What the unit rate covers
- Precast kerbstones of the specified size
- Excavation and trimming the trench bottom
- Concrete bed and haunching
- Joint mortar and pointing
- Setting to line and level, and curing
- Breakage and cutting waste
Priced separately
- Base course under the road
- Kerb painting
- Storm drainage channels and inlets
- Removal of old kerbstones
Specification and reference
Governed by the project specification and by the standards of the municipality or road owner for sizes and compressive strength. Kerbstones from an approved plant are laid on a concrete bed and haunched behind before asphalt or paving is placed. The accessibility requirements of the Saudi Building Code SBC 201 are observed at kerb ramps and pedestrian crossings.
What moves the rate
- Kerb size and strength
- Proportion of curves and special units
- Volume of concrete bed and haunching in the section
- Length and continuity of the work
Common pricing mistakes
- Pricing the kerb alone and leaving out the concrete bed and haunching, whose volume in the section can approach that of the kerb itself.
- Calculating the number of units from total length without allowing for short and cut units on curves and at vehicle entrances.
- Carrying the rate of a small garden edging kerb from an earlier project over to a larger, heavier road kerb.
- Forgetting two-colour kerb painting where the municipality requires it, or assuming it is within the rate without any wording.
Related calculators and terms
More items in Paving
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل