Epoxy floor coating in the bill of quantities
| Unit | m² (or lin. m for coved skirtings) |
|---|---|
| Category | Painting |
| Division | Plaster, paint and gypsum works |
The item as worded in the bill
Supply and apply an epoxy coating system to concrete floors to the specified total dry film thickness, comprising surface preparation by mechanical grinding or shot blasting, one coat of penetrating epoxy primer and two coats of solvent-free two-component epoxy in the approved colour, with treatment of cracks and joints; the rate includes concrete moisture testing.
Method of measurement
Measured in square metres of net horizontal area coated between walls, deducting equipment plinths, columns and uncoated areas. Coved skirtings or coating turned up the wall are measured in linear metres under a separate item, as are line markings and lanes. No area is added for multiple coats or for higher consumption on a rough surface, and surface preparation is within the item, not measured separately.
What the unit rate covers
- Surface preparation by grinding or blasting and vacuuming of dust
- Moisture testing of the concrete before application
- Primer and repair of cracks and pits with epoxy filler
- Epoxy coats to the required thickness
- Closing off and protecting the area until fully cured
Priced separately
- Coved skirtings and line markings
- Repair of weak concrete or a new levelling screed
- Sealant to expansion and sawn joints
- A moisture barrier coat against rising damp, if needed
Specification and reference
Applied to the project specification and the manufacturer’s data sheet for mixing ratios, pot life, thickness and curing time before use. The concrete must be fully cured and dry, sound and free of oil and surface laitance. Slip- and chemical-resistance certificates are requested to suit the use, and floor finishes fall under the Saudi general building code SBC 201.
What moves the rate
- Required thickness and system type, from thin coating to self-levelling
- Condition of the concrete and extent of preparation and repair
- Uninterrupted area and freedom to work without obstructions
- Special requirements such as chemical resistance or static conductivity
Common pricing mistakes
- Confusing thin roller-applied epoxy coating with a self-levelling system 2 to 3 mm thick, which differ greatly in material consumption.
- Ignoring the cost of grinding or blasting and dust-extraction equipment, which is a core part of the item and not free preliminary work.
- Pricing without inspecting the floor, then finding weak or oil-contaminated concrete that needs repair and additional primer coats.
- Forgetting the coved skirting at floor-to-wall junctions in kitchens and food stores, which is usually required and measured in linear metres.
Related calculators and terms
More items in Painting
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل