Excavation in the bill of quantities

Excavation covers removing soil to reach the founding level: excavation for isolated footings and tie beams, open bulk excavation for a basement or raft, trenches for service lines, and excavation in rock. It is done with excavators and loaders in ordinary soil and with hydraulic breakers in rock, since blasting is not allowed inside built-up districts. The soil report decides the type of plant, the slope of the sides and the need for shoring or dewatering, so it is read before pricing any item in this category.

Where it sits in the bill and what comes before it on site

Excavation items come after site preparation and before plain concrete. Digging does not start until the setting-out of axes and levels is approved, buried services are located, the condition of neighbouring buildings is recorded and a stockpile area for material suitable for backfill is agreed.

Items in this category

ItemUnit
Excavation for footings and foundationsm³
Bulk excavation for basementsm³
Excavation in rockm³
Trench excavation for serviceslin. m by depth band (or m³)

What is often left out when pricing it

Frequently asked questions

Is working space around footings paid within the excavation quantity?

In most contracts in the Kingdom excavation is measured on the net dimensions of the blinding multiplied by the depth, and working space and slopes are carried in the unit rate. Some preambles add a set width on each side, so the wording is checked before the rate is built.

How is excavation in ordinary soil told apart from rock when it comes to payment?

Specifications usually define rock as material that an excavator cannot remove without a hydraulic breaker. When it appears, digging stops, its surface level is surveyed in the engineer’s presence and a record is signed; its volume is then calculated from that level to the bottom of excavation and paid at the rock rate.

Is disposal of surplus excavated material included in the excavation rate?

Usually yes; the customary description includes hauling the surplus to approved dumps whatever the distance. Some bills, however, give haulage its own item per cubic metre, and some oblige the contractor to stockpile material suitable for backfill on site. Haulage is worked out on the bulked volume, not the geometric volume of the excavation.

Related calculators and terms

Other categories in Site preparation and earthworks

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل