Septic tank and soakaway in the bill of quantities
| Unit | No. (or lump sum) |
|---|---|
| Category | Sewage disposal and rainwater |
| Division | Plumbing and drainage |
The item as worded in the bill
Supply and construct a two-compartment septic tank and a soakaway pit to the dimensions on the drawings, with base, walls and roof in reinforced concrete with sulphate-resisting cement for the septic tank and open-jointed solid block walls for the soakaway; the rate includes excavation and carting away, waterproofing, suction manholes with cast iron covers, the vent pipe and connecting pipes.
Method of measurement
Measured by number or lump sum for the complete structure to the drawing dimensions, and not remeasured unless the engineer changes the dimensions or depth in writing. Where the bill separates the components, excavation and concrete are measured in cubic metres, blockwork and waterproofing in square metres, and covers by number. Rock excavation and dewatering merit an extra item when met without having been in the soil report.
What the unit rate covers
- Excavation, carting away and backfilling around the structure
- Concrete, reinforcement and blockwork
- Internal and external waterproofing of the septic tank
- Suction manholes and covers
- Vent pipe, connecting pipes and internal baffles
Priced separately
- Drain line from the last inspection chamber to the tank
- Rock excavation and dewatering
- Tanker emptying during operation
Specification and reference
Governed by the private sewage disposal code SBC 702 and by municipal requirements for distance from property boundaries, foundations and the potable water tank; concrete follows SBC 304 with sulphate-resisting cement to ASTM C150 Type V. Capacity follows the number of users and the leaching area by the soil percolation test, and permeable disposal is prohibited where groundwater is high.
What moves the rate
- Dimensions and total depth
- Soil type: sandy, rock, sabkha
- Permeable or sealed and waterproofed
- Groundwater level and the need to support the excavation sides
Common pricing mistakes
- Pricing the soakaway for excavation in ordinary soil, then meeting rock at shallow depth with no contract item for it.
- Forgetting that excavation depth is governed by the inlet pipe level, not ground level, so actual depth exceeds the effective depth.
- Omitting support to the sides of a deep excavation near the building foundations or the neighbour’s wall: a safety condition not paid for separately.
- Treating the roof slab as an ordinary slab; it carries the fill above and possibly a vehicle, so needs heavier reinforcement and thickness.
Related calculators and terms
More items in Sewage disposal and rainwater
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل