Inspection chambers in the bill of quantities
| Unit | No. |
|---|---|
| Category | Soil and waste drainage |
| Division | Plumbing and drainage |
The item as worded in the bill
Supply and construct a sewer inspection chamber, internal size 60×60 cm and up to 100 cm deep, with a plain concrete base and walls of concrete or solid block, internal render in sulphate-resisting mortar, channel and benching formed in the bottom, and an airtight cast iron cover and frame; the rate includes excavation, backfilling and external bitumen coating.
Method of measurement
Measured by number, each internal size and each depth band separately, the depth being taken from cover level to channel invert. Where the depth exceeds the band in the description, the chamber is priced in the next band, or a depth extra is added where such an item exists. Chambers with heavy-duty covers under vehicle routes are kept apart from those in yards and walkways.
What the unit rate covers
- Excavation, backfilling and compaction around the chamber
- Base, walls and cover slab where required
- Internal render and benching
- Cover and frame of the specified load class
- External coating and pipe entry and exit openings
Priced separately
- Drain pipes between chambers
- Dewatering where groundwater is met
- Reinstating asphalt or paving over the trench
Specification and reference
SBC 701 places chambers at changes of direction, gradient and diameter and within the maximum spacing between two cleaning points. Concrete follows SBC 304, with sulphate-resisting cement in sabkha soil or where salts are high. The cover load class is chosen by location to EN 124, and chamber dimensions increase with depth to allow entry and cleaning.
What moves the rate
- Internal size and depth
- Cover load class: pedestrian or vehicular
- Soil type and groundwater level
- Cast in situ or precast
Common pricing mistakes
- Pricing all chambers at the minimum depth, although the fall deepens each chamber after the previous one up to the connection point.
- Placing a light-duty cover in the vehicle path inside the yard; it breaks after handover and the contractor must replace it under warranty.
- Leaving out the internal render and the half-round channel in the bottom, fine labour that takes longer than building the walls.
- Not allowing for the last chamber at the property boundary and the connection to the public sewer with the operator’s requirements.
Related calculators and terms
More items in Soil and waste drainage
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل