Plot boundary wall in the bill of quantities
| Unit | lin. m |
|---|---|
| Category | Parapets and boundary walls |
| Division | Masonry works |
The item as worded in the bill
Supply and construct a plot boundary wall 3.00 m high above pavement level, comprising strip footings, ground beam, reinforced concrete columns at about 3 m centres with 20 cm hollow concrete block infill and a top beam, with expansion joints as shown on the drawings; the rate includes excavation, backfilling, concrete, steel, blockwork and bituminous coating to buried parts.
Method of measurement
Measured by the linear metre on the wall centre line, stating height above a defined reference level, gate openings deducted. Each different height has its own item. Footings and columns are not measured separately in a composite item. In detailed bills, excavation and concrete go by the cubic metre and blockwork and plaster by the square metre, each in its section. Length is checked against the approved site plan.
What the unit rate covers
- Excavation, backfilling, compaction and removal of surplus
- Blinding, footings, ground beam, columns and top beam
- Steel reinforcement and formwork
- 20 cm blockwork between columns
- Bituminous coating to buried parts
- Expansion joints
Priced separately
- Plaster and paint or stone cladding
- Metal gates and their own columns
- Lighting and electrical work on the wall
- The retaining portion where levels differ
Specification and reference
The municipality’s building requirements set the maximum wall height, its position relative to the property line and its street-face appearance. Footings are designed to the soil report and SBC 303, concrete to SBC 304 and blockwork to SBC 305, with the wind loads of SBC 301. Sulphate-resisting cement is used in buried parts where the soil report recommends it.
What moves the rate
- Wall height and founding depth
- Soil conditions and level difference between the plot and its surroundings
- Column spacing and concrete sections
- Nearness to existing buildings, which forces hand excavation
Common pricing mistakes
- Pricing the linear metre on a single height although the street slope or the neighbour’s level raises the actual height.
- Assuming a symmetrical footing although a footing on the property line cannot extend into the neighbour’s land, so it is eccentric and heavier.
- Accepting the length of all four sides without checking whether a neighbour’s wall already stands on one of them.
- Forgetting the gate columns, larger in section and reinforcement, and deducting the gate opening without pricing its beam and columns.
Related calculators and terms