Floor screed in the bill of quantities
| Unit | m² (or m³ for screeds to falls) |
|---|---|
| Category | Screeds and terrazzo |
| Division | Flooring and cladding |
The item as worded in the bill
Supply and lay cement–sand floor screed of 5 cm average thickness, of Portland cement and clean graded sand in a semi-dry consistency, laid on the concrete slab after cleaning, dampening and applying a cement bonding slurry, ruled off to the stated levels and falls and trowelled, including control joints and water curing, ready to receive the final finish.
Method of measurement
Measured in square metres of net area laid between walls with the average thickness stated, deducting columns and plinths. Each different thickness is measured under a separate item. Screeds to falls of varying thickness on roofs and in bathrooms are measured in square metres at average thickness or in cubic metres as the bill provides. Mesh, fibres, perimeter strip and bonding slurry are not measured separately unless stated.
What the unit rate covers
- Cement, sand, mixing and hoisting to the floors
- Cleaning and dampening the slab and bonding slurry
- Setting levels and falls with dots and straightedge
- Trowelling or roughening to suit the following finish
- Control joints and water curing
Priced separately
- Thermal insulation or waterproofing beneath the screed
- Reinforcing mesh where a separate item exists
- Self-levelling compound over the screed
- Filling of structural expansion joints
Specification and reference
The project specification fixes mix proportions or strength, thickness and flatness. Cement complies with ASTM C150 and sand is clean, graded and salt-free. Screed materials are classified under EN 13813 where specified. It is cured by water or covering for several days and protected from rapid drying in hot weather; the general provisions of the Saudi code SBC 201 apply.
What moves the rate
- Average thickness and slab level differences
- Bonded screed or floating over insulation
- Means of hoisting materials to upper floors
- Flatness required by the following finish
Common pricing mistakes
- Pricing the nominal thickness on the drawings without surveying the as-built slab levels; casting tolerances make the real average greater.
- Ignoring the cost of raising sand and cement to upper floors by hoist or pump, which multiplies in towers.
- Allowing one thickness for the whole floor, although bathrooms and kitchens need more to cover drainage pipes and form falls.
- Forgetting that a floating screed over insulation needs mesh or fibres and greater thickness, and pricing it at the thin bonded-screed rate.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: Black National Cement
Related calculators and terms
More items in Screeds and terrazzo
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل