Steel structure for warehouses and hangars in the bill of quantities
| Unit | tonne (or m² of covered area) |
|---|---|
| Category | Structural steelwork |
| Division | Metal and steel works |
The item as worded in the bill
Supply, fabricate and erect steel structure for a warehouse of 30 m clear span, of frames fabricated from steel plates, with cold-formed purlins and girts, bracing and connections, including anchor bolts, high-strength bolts, blast cleaning, primer and two finishing coats, shop drawings, structural calculations and lifting equipment.
Method of measurement
Measured by tonne on the net weight calculated from the approved shop drawings: section lengths by their mass per metre, and plate areas by thickness and steel density of 7850 kg/m³. Nothing is added for welds, cutting waste or rolling tolerances. Bolts are treated as the preambles state. Where measurement is by square metre, the plan area of the building to its outer edges is taken.
What the unit rate covers
- Shop drawings and structural calculations
- Supply, fabrication and welding of steel
- Surface preparation and paint system
- Anchor bolts and bolts
- Transport, cranes, erection and alignment
- Weld inspection and paint touch-up after erection
Priced separately
- Concrete footings and pedestals
- Roof and wall covering
- Fire-resistant coating, if required
- The overhead crane and its equipment
Specification and reference
It is designed and executed to SBC 306 for steel structures, with loads taken from SBC 301 including wind and earthquake. The specification defines the steel grade, such as ASTM A36 for rolled sections and ASTM A572 for high-strength plates, the paint system and its dry film thickness, and weld inspection requirements.
What moves the rate
- Clear span and eave height
- Presence of an overhead crane or mezzanine
- Paint system or galvanising
- Project location and ease of crane movement
Common pricing mistakes
- Carrying the weight per square metre from a previous warehouse to a building with a different span or height or an overhead crane.
- Weighing the main frames only and forgetting purlins, girts, bracing, base plates and connections.
- Dropping the anchor bolts, which are supplied early and cast with the footings weeks before the rest of the structure arrives.
- Pricing a shop primer only, while the specification requires a full paint system of a stated dry film thickness or hot-dip galvanising.
Related calculators and terms
More items in Structural steelwork
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل