Soil and waste drainage in the bill of quantities
The drainage network collects soil from water closets and waste water from basins and floors and conveys it by gravity to the inspection chambers and then to the public sewer or septic tank, together with the vent stacks that protect the water seal in the traps. The prevailing material in Saudi Arabia is uPVC pipe with solvent-cement joints inside the building and rubber-ring joints for buried lines; high-density polyethylene or sound-attenuating pipes are used in towers, hotels and hospitals, and cast iron where fire resistance is required.
Where it sits in the bill and what comes before it on site
Its items come first in the plumbing bill. Ground lines are laid after backfilling and compacting between the ground beams and before casting the ground slab, upper-floor lines are hung below the slabs once formwork is struck, and floor drains are set before bathroom waterproofing.
Items in this category
| Item | Unit |
|---|---|
| uPVC drainage pipes | lin. m (or per point) |
| Floor drains | No. (or lin. m for linear drains) |
| Inspection chambers | No. |
What is often left out when pricing it
- Vent stacks and their extension above the roof with a cowl: full pipes that do not appear on bathroom plans.
- Cleanouts and their covers at every change of direction, at the foot of every stack and on long horizontal runs.
- Testing the network by filling it with water before backfilling or closing in, and retesting after any joint is repaired.
- Galvanised hangers and brackets for lines suspended below slabs, and fire collars where pipes cross fire-rated separations.
Frequently asked questions
Do I price drainage by linear metre or per point?
Both occur. Villas are commonly priced per point for each fixture, covering the pipe up to the stack or inspection chamber; large projects are measured in linear metres per diameter, fittings included. When pricing per point, take the actual average length from the drawings: a bathroom beside the stack differs widely from a distant one.
What falls must I keep on horizontal lines?
The plumbing code sets a minimum fall that varies with diameter and is greater for small diameters. For the estimator, the fall uses up height available below the slab or within the fill: the longer the horizontal run, the deeper the excavation or the lower the false ceiling, and deeper inspection chambers may be needed.
Are excavation and backfilling for external drain lines included in the pipe rate?
It varies between bills. Many government bills state that the rate per metre of buried lines includes excavation, sand bedding, backfilling and compaction; others give separate items under earthworks. If the description is silent, raise a query before submitting the tender; otherwise the safer assumption is that they are included in the rate.
Related calculators and terms
Other categories in Plumbing and drainage
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل