Fire-rated door in the bill of quantities
| Unit | No. |
|---|---|
| Category | Steel and fire-rated doors |
| Division | Doors, windows and aluminium |
The item as worded in the bill
Supply and install single-leaf steel door, fire-rated for 90 minutes, size 100×220 cm, leaf of 1.2 mm galvanised steel sheet with rock wool core, frame of 1.5 mm steel sheet grouted with mortar, with smoke seals, including hinges, self-closer, emergency push bar and test label, from a factory approved by Civil Defense.
Method of measurement
Measured by number per type according to the door schedule and the life-safety plan, the description stating the rating period, size, number of leaves and any vision panel. Each rating period is a separate type even if the size is the same. It is not measured by square metre, and the hardware set is part of the item where stated, being part of the tested assembly.
What the unit rate covers
- Leaf and frame bearing the rating label
- Wall anchors and grouting of the frame
- Intumescent and smoke seals
- Hinges, self-closer and lock or push bar as described
- Primer and two finishing coats
- Test certificates and approval documents
Priced separately
- Magnetic door holders and their connection to the fire alarm system
- Access control system
- Fire stopping around services in the fire-rated wall
Specification and reference
SBC 201 and SBC 801 set the door’s rating period according to the rating of the wall in which it sits. The door is supplied as a tested assembly bearing a label from a recognised body and installed to NFPA 80 without any site modification; approval of the factory and product by Civil Defense is required before supply.
What moves the rate
- Required rating period
- Number of leaves and size
- Area of the vision panel in fire-rated glass
- Hardware set content: push bar and closer
Common pricing mistakes
- Pricing leaf and frame only and forgetting the listed hardware set, although a door without a self-closer is rejected at inspection.
- Assuming a vision panel can be cut or the leaf trimmed on site; this voids the rating label and the door must be replaced.
- Grouping 60- and 90-minute doors under one rate, although core, glass and certification differ between them.
- Relying on a quotation from an unapproved workshop, so the submittal is rejected and the purchase repeated at a higher rate and longer lead time.
Related calculators and terms