Curtain wall in the bill of quantities
| Unit | m² |
|---|---|
| Category | Glazed facades and metal cladding |
| Division | Doors, windows and aluminium |
The item as worded in the bill
Supply and install curtain wall in stick system of thermally broken aluminium sections with powder coating, double glazed with 8 mm tempered glass + 16 mm cavity + 6 mm low-emissivity glass, including fixing brackets and anchors, insulated spandrel panels, fire stops at slab edges, sealants, structural calculations, shop drawings and mock-up.
Method of measurement
Measured by square metre on the net facade area taken on its face between its outer edges, including vision and spandrel zones, with no deduction for mullions or opening vents. Corners are measured on their developed length. Entrance doors within the facade are counted by number in separate items. Glass cutting waste, brackets and anchors are not measured; all are carried in the unit rate.
What the unit rate covers
- Structural calculations and shop drawings
- Mullions, transoms, brackets and anchors
- Double-glazed units
- Spandrel panels and their insulation
- Gaskets, sealants and flashings
- Mock-up, water penetration test and access equipment
Priced separately
- Entrance doors and power-operated sliding doors within the facade
- Facade cleaning equipment
- Internal blinds
- Secondary steel structure for high openings
Specification and reference
It is designed for wind loads under SBC 301 and is subject to SBC 201 requirements for safety glass and fire stops at slab edges, and to the thermal performance limits of SBC 601. The project specification calls for air permeability, water penetration and structural tests on a mock-up, and approved calculations for sections and glass.
What moves the rate
- System: stick, unitised or structural glazing
- Glass make-up and thickness
- Storey height and mullion depth
- Building height and means of access
Common pricing mistakes
- Pricing a tower at the square-metre rate of a low-rise building, although wind pressure at height demands deeper mullions and thicker glass.
- Leaving out slab-edge fire stops and spandrel insulation on the assumption that they belong to another contractor.
- Measuring vision zones only and forgetting spandrels, parapet returns and column casings belonging to the same system.
- Overlooking the cost of lifting platforms, mock-up and tests listed in the specification but having no items in the bill.
Related calculators and terms
More items in Glazed facades and metal cladding
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل