Split air conditioning in the bill of quantities
Split air conditioning is the most common system in villas, flats and small offices: an indoor and an outdoor unit joined by two copper lines and a control cable. The wall-mounted unit is simpler and cheaper to install and suits single rooms. The concealed unit sits above the suspended ceiling and feeds short ducts and outlets; it suits halls and reception rooms needing a ceiling clear of visible units. Capacity is set by a heat-load calculation for each space, and inverter compressors are preferred to save energy.
Where it sits in the bill and what comes before it on site
Split unit items appear in the mechanical section after the first-fix items. Copper piping, condensate drains and power points must be installed and tested before plastering, and painting, suspended ceilings and outdoor unit bases must be complete before the units are fixed.
Items in this category
| Item | Unit |
|---|---|
| Wall-mounted split unit | No. |
| Ducted (concealed) split unit | No. |
What is often left out when pricing it
- Copper lengths beyond the length covered by the unit rate, especially when outdoor units sit on the roof.
- The additional refrigerant charge required when the piping run exceeds the factory pre-charged length.
- Outdoor unit bases or brackets, vibration pads, and coring through walls and making good.
- Access panels in the suspended ceiling under concealed units, and the wired thermostat with its conduit.
Frequently asked questions
Does the rate for a split unit include the copper piping?
The rate usually includes a stated length of insulated copper and control cable, written in the item description; anything beyond it is paid per linear metre. The actual route between the two units, vertical runs included, should therefore be measured from the drawings before the unit rate is fixed.
How are split units measured in the bill of quantities?
They are measured by number, classified by type and cooling capacity, with a separate item for each capacity. Wall-mounted and concealed units are not combined in one item, because their hanging, ducting, outlets and access requirements differ enough to change the unit rate.
When is first fix priced separately from supplying the units?
When the bill separates the first-fix stage from supply and installation, or when the owner supplies the units himself. Copper, drains and electrical boxes are then priced as separate items, and the unit item is limited to fixing, evacuation, charging, start-up and testing.
Related calculators and terms
Other categories in HVAC and fire fighting
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل