HomePayment Certificate Calculator

Payment Certificate Calculator

Work out the net amount due on an interim payment certificate after retention, advance payment recovery and VAT — the way a Saudi IPC is actually built up.

Calculator

💡 Attach a jointly measured, signed quantity sheet to every certificate — an interim certificate without approved measurements almost always comes back for review.

How the calculation works

Work executed this period = cumulative value to date minus the cumulative total of the previous certificates. Retention and the advance-payment recovery percentage are deducted from that period value, VAT is calculated on the period value, and what remains is the net payable.

Frequently asked questions

Why is a payment certificate calculated cumulatively?

Because quantities are measured cumulatively from the start of the project and everything previously certified is then deducted. An error in an earlier certificate self-corrects in the next.

When is retention released?

Commonly half at preliminary handover and the balance at final acceptance once the defects liability period ends. The contract wording governs, so read the clause before you assume.

How is the advance payment recovered?

Usually as a fixed percentage of each certificate until the advance is fully repaid, sometimes starting only once progress passes an agreed threshold. That rate is the input here.

Is VAT charged on the amount after retention?

No. VAT is due on the value of work executed in the period; retention is a deduction from the payment, not from the taxable value of the work.

Need a whole bill of quantities priced, not one material?

Upload your BOQ and get every line priced at Saudi market rates in minutes — VAT and all.

Start free

More free calculators

This calculator is also available in Arabic: حاسبة المستخلص.