Project Duration Calculator

Estimate how many months your building will take from its area and type, using completion rates seen on Saudi villa, residential and commercial projects.

Calculator

💡 Tie the payment schedule to clear completion milestones in the contract itself — steady cash is the strongest schedule accelerator there is.

How the calculation works

Duration is roughly the mobilisation period plus area divided by the monthly completion rate in square metres per month. Indicative single-crew rates: villas 60-90, residential buildings 250-400, commercial 300-500 m2 per month. A second crew shortens the build, but not proportionally.

Frequently asked questions

Why do projects overrun these figures?

Late owner decisions, finishing selections above all, interrupted payments and design changes. Those three outweigh weather and labour supply put together.

Does doubling the workforce halve the duration?

No. Technical sequencing — no plaster before first fix — and crowded work fronts cap the gain. Running trades in parallel on separate fronts works; stacking men on one does not.

Does the estimate include design and permits?

Only the mobilisation months you enter. Municipal permitting and design approval run before site works and should be added on top of the figure shown.

How do I turn months into a contractual completion date?

Add the mobilisation period to the site handover date, then allow for Ramadan, Eid holidays and the testing and commissioning period before you commit to a date.

Need a whole bill of quantities priced, not one material?

Upload your BOQ and get every line priced at Saudi market rates in minutes — VAT and all.

Start free

More free calculators

This calculator is also available in Arabic: حاسبة مدة المشروع.