العربية Start free
Home ‹ Knowledge ‹ What Is a Snag List (Punch List)

What Is a Snag List (Punch List)?

A snag list is the schedule of defects and incomplete work recorded by the consultant before handover — closing it is the condition of taking over and of releasing retention.

On this pageIts place in the handover cycleManaging it intelligentlyIts financial weightWorked exampleFAQ

Its place in the handover cycle

When preliminary handover is requested, an inspection is held and its observations — unfinished finishes, installation defects, systems not commissioned — are recorded in a snag or punch list. The contractor works through them and they are closed item by item until handover is granted and the defects liability period begins.

Managing it intelligently

A self-inspection before calling the consultant in shortens the formal list; and sorting the observations by area and trade, with owners and deadlines against each, turns the chaos of the final stretch into a fast, methodical close-out.

Its financial weight

Handover usually releases half the retention and stops delay damages running, so every day the list holds handover up costs cash directly. Closing it quickly is an investment, not a courtesy.

Worked example

On a residential tower, the handover inspection recorded 642 observations across three trades; a dedicated team closed them in 21 days with daily tracking by area — handover was granted and SAR 1.1 million of retention was released on time.

FAQ

What is the difference between preliminary and final handover?

Preliminary handover comes when the works are complete and the snags are closed, and starts the defects liability period, usually a year. Final handover follows if no defects have appeared, releasing the remaining retention and ending the principal obligations.

Put this to work with Construction Project Management

Manage your construction project from award to handover: execution, cost and resources in one board

Explore Construction Project Management

Related topics

Also in Arabic