How to Obtain a Building Permit in Saudi Arabia

A building permit is a municipal authorisation that precedes any construction work, issued electronically once drawings are approved by a licensed engineering office and the site requirements are met.

On this pageThe general routeRequirements that drive costAfter the permitRecurring mistakesWorked exampleFAQ

The general route

It starts with a licensed engineering office preparing the drawings in line with the building requirements for the plot and the city’s building regulations. The applications are then submitted electronically through the Balady platform with the title deed, the owner’s details and the project drawings. After review and payment the permit is issued with a stated validity, followed by the obligation of engineering supervision during execution.

Requirements that drive cost

Read the plot requirements before designing: the building ratio, the setbacks, the height, the number of floors, the parking, and in some developments the façade specifications. These determine the buildable area, and so determine the viability of the whole project before a single drawing is made.

After the permit

The permit is not the end of the procedures: there is the engineering supervision and its periodic reports, the coordination with the utility providers for power and water, and then the building completion certificate required later for permanent connection or for dealing in the property. Allow for these periods inside your programme, not outside it.

Recurring mistakes

The commonest: starting excavation before the permit is issued; breaching the setbacks and only discovering it at the survey; and building an unpermitted extension that later blocks the completion certificate. Each of them costs demolition and rebuilding far dearer than the wait would have been.

Worked example

The owner of a 600 m² plot in a residential district found that the building ratio and setbacks allowed a ground floor of 340 m², not the 480 he had assumed. Adjusting the design early, before pricing, saved him a complete redraw and four weeks of delay.

FAQ

How long does a permit usually take?

It varies by municipality and by how complete the file is, and the decisive factor is the quality of the engineering office’s preparation: a file compliant with the requirements first time shortens the review cycles more than any amount of chasing.

Do I need a permit for refurbishment and finishing?

Refurbishment that touches the structure or changes areas or façades needs a permit, while purely internal finishing work is treated differently. Check your municipality’s requirements before you start, not after.

How does the Saudi Building Code relate to the permit?

Approved drawings must comply with the Saudi Building Code on structure, fire, energy efficiency and more, and those obligations feed directly into the materials and the cost.

Put this to work with Construction Project Management

Manage your construction project from award to handover: execution, cost and resources in one board

Explore Construction Project Management

Related topics

Also in Arabic