Site Handover تسليم الموقع
Definition
Giving the contractor possession of the site free of obstruction so execution can begin, recorded in a minute describing its condition and boundaries — and from which the contract period runs, not from signature.
Example
Site possession was 22 days late, so the contractor was granted a matching extension.
Where it is used
An obligation on the employer whose breach earns time and compensation.
Related terms
From the term to the work